Welcome to your Estimation And Costing Exam Set 1

Name
1. 
Pick up the excavation where measurements are made in square metres for payment.

2. 
The order of booking dimensions is

3. 
Pick up the item of work not included in the plinth area estimate

4. 
The brick work is measured in sq metre, in case of

5. 
Brick walls are measured in sq. m if the thickness of the wall is

6. 
In long and short wall method of estimation, the length of long wall is the centre to centre distance between the walls and

7. 
While preparing a detailed estimate

8. 
The expected out turn of cement concrete 1 : 2 : 4 per mason per day is

9. 
The plinth area of a building not includes

10. 
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is

11. 
The item of the brick structure measured in sq.m, is

12. 
The item of steel work which is measured in sq.m, is

13. 
The most reliable estimate is

14. 
The expected out turn of 12 mm plastering with cement mortar is

15. 
The damp proof course (D.P.C.) is measured in

16. 
The area is measured correct to the nearest

17. 
The volume is measured correct to the nearest

18. 
The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as

19. 
Pick up the incorrect statement from the following

20. 
The measurement is not made in square metres in case of

21. 
The detention period in a septic tank is assumed

22. 
For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is

23. 
For the construction of buildings, the subheads of the estimate are

24. 
The ‘centre line method’ is specially adopted for estimating

25. 
Referring of given figure, pick up the correct statement from the following: